What are the stages of hydropower development?
32 views
- a) Feasibility, Design, Construction, Operation
- b) Planning, Design, Procurement, Commissioning
- c) Identification, Feasibility, Construction, Operation
- d) Pre-feasibility, Feasibility, Design, Construction, Operation (Correct Answer)
Explanation
Explanation: The stages of hydropower development are Pre-feasibility, Feasibility, Design, Construction, and Operation. In the pre-feasibility stage, the potential of the hydropower project is identified and evaluated. In the feasibility stage, the technical, economic, financial, and environmental viability of the project is assessed. In the design stage, the detailed engineering design of the project is prepared. In the construction stage, the project is constructed, and in the operation stage, the project is operated and maintained.