Hydropower MCQs for Engineering License NEC / Loksewa / ME Exams
30 Hydropower multiple-choice questions with answers and explanations, from the ExamsNepal question bank for Engineering License NEC / Loksewa / ME Exams. Try each question first, then open the answer to check your reasoning.
Preparing for NEC Architecture Engineering License Exam, NEC Civil Engineering License Exam or NEC Electronics, Communication & Automation Engineering License Exam? See the exam pattern, syllabus and free mock tests.
1. What are the stages of hydropower development?
- A. a) Feasibility, Design, Construction, Operation
- B. b) Planning, Design, Procurement, Commissioning
- C. c) Identification, Feasibility, Construction, Operation
- D. d) Pre-feasibility, Feasibility, Design, Construction, Operation
Discuss this questionShow answer & explanation
Answer: D. d) Pre-feasibility, Feasibility, Design, Construction, Operation
Explanation: The stages of hydropower development are Pre-feasibility, Feasibility, Design, Construction, and Operation. In the pre-feasibility stage, the potential of the hydropower project is identified and evaluated. In the feasibility stage, the technical, economic, financial, and environmental viability of the project is assessed. In the design stage, the detailed engineering design of the project is prepared. In the construction stage, the project is constructed, and in the operation stage, the project is operated and maintained.2. What is the power potential of Nepal and the world?
- A. a) Nepal: 83,000 MW, World: 1.2 million MW
- B. b) Nepal: 83,000 MW, World: 12 million MW
- C. c) Nepal: 43,000 MW, World: 1.2 million MW
- D. d) Nepal: 43,000 MW, World: 12 million MW
Discuss this questionShow answer & explanation
Answer: C. c) Nepal: 43,000 MW, World: 1.2 million MW
Explanation: Nepal has a technically feasible hydropower potential of about 83,000 MW, but the economically feasible potential is estimated to be about 43,000 MW. The power potential of the world is estimated to be about 1.2 million MW.3. What is the history of hydropower development in Nepal?
- A. a) Hydropower development started in Nepal in the 1960s
- B. b) Hydropower development started in Nepal in the 1970s
- C. c) Hydropower development started in Nepal in the 1980s
- D. d) Hydropower development started in Nepal in the 1990s
Discuss this questionShow answer & explanation
Answer: B. b) Hydropower development started in Nepal in the 1970s
Explanation: Hydropower development started in Nepal in the 1970s with the commissioning of the 500 kW Pharping hydropower plant. Since then, several small and large hydropower projects have been developed in Nepal.4. What are the policies, acts, and regulations related to hydropower development in Nepal?
- A. a) Hydropower Development Policy 2001, Electricity Act 1992, Electricity Regulation 1993
- B. b) Hydropower Development Policy 1992, Electricity Act 2001, Electricity Regulation 2002
- C. c) Hydropower Development Policy 1992, Electricity Act 1992, Electricity Regulation 1993
- D. d) Hydropower Development Policy 2001, Electricity Act 2001, Electricity Regulation 2002
Discuss this questionShow answer & explanation
Answer: D. d) Hydropower Development Policy 2001, Electricity Act 2001, Electricity Regulation 2002
Explanation: The policies, acts, and regulations related to hydropower development in Nepal are the Hydropower Development Policy 2001, Electricity Act 2001, and Electricity Regulation 2002. These policies, acts, and regulations provide the legal and regulatory framework for hydropower development in Nepal.5. What is the difference between power and energy in the context of hydropower plants?
- A. a) Power is the rate at which energy is generated, while energy is the total amount of work done over a period of time.
- B. b) Power and energy are the same thing in the context of hydropower plants.
- C. c) Power is the total amount of work done over a period of time, while energy is the rate at which work is done.
- D. d) None of the above.
Discuss this questionShow answer & explanation
Answer: A. a) Power is the rate at which energy is generated, while energy is the total amount of work done over a period of time.
Explanation: In the context of hydropower plants, power refers to the rate at which energy is generated or the rate at which work is done. It is usually measured in watts (W) or kilowatts (kW). Energy, on the other hand, refers to the total amount of work done over a period of time and is usually measured in watt-hours (Wh) or kilowatt-hours (kWh).6. Which of the following is not a method of fixing the installed capacity of a hydropower plant?
- A. a) Run-of-the-river method
- B. b) Storage method
- C. c) Pondage method
- D. d) Thermal method
Discuss this questionShow answer & explanation
Answer: D. d) Thermal method
Explanation: The thermal method is not a method of fixing the installed capacity of a hydropower plant. The other three methods - run-of-the-river, storage, and pondage - are commonly used to determine the installed capacity of a hydropower plant.7. Which type of hydropower plant uses the natural flow of a river to generate electricity?
- A. a) Run-of-the-river plant
- B. b) Pumped storage plant
- C. c) Storage plant
- D. d) Pondage plant
Discuss this questionShow answer & explanation
Answer: A. a) Run-of-the-river plant
Explanation: A run-of-the-river hydropower plant uses the natural flow of a river to generate electricity. It does not require a large reservoir or dam, but instead uses the natural flow of the river to turn turbines and generate electricity.8. What are the main components of a hydropower project?
- A. a) Dam, powerhouse, transmission lines
- B. b) Turbine, generator, penstock
- C. c) Intake, spillway, tailrace
- D. d) All of the above
Discuss this questionShow answer & explanation
Answer: D. d) All of the above
Explanation: The main components of a hydropower project include a dam, intake structure, penstock, turbine, generator, powerhouse, spillway, tailrace, and transmission lines.9. What is the purpose of regulating reservoirs in a hydropower project?
- A. a) To control the flow of water to the turbines and generate electricity
- B. b) To prevent floods and regulate downstream flow
- C. c) To store water for future use
- D. d) All of the above
Discuss this questionShow answer & explanation
Answer: B. b) To prevent floods and regulate downstream flow
Explanation: The main purpose of regulating reservoirs in a hydropower project is to prevent floods and regulate downstream flow. The reservoir can store water during periods of high flow and release it during periods of low flow, which helps to prevent flooding downstream. It can also regulate the downstream flow to maintain a constant flow rate, which is important for downstream users such as irrigation systems and municipal water supplies.10. What are the components of a typical storage plant?
- A. a. Dam, powerhouse, switchyard, surge tank
- B. b. Surge tank, switchyard, transmission line, tailrace
- C. c. Dam, powerhouse, intake, outlet
- D. d. Outlet, transmission line, switchyard, surge tank
Discuss this questionShow answer & explanation
Answer: C. c. Dam, powerhouse, intake, outlet
Explanation: A typical storage plant consists of a dam, powerhouse, intake structure, and outlet structure. The dam is constructed across a river or a stream to create a reservoir for storing water. The intake structure is designed to collect water from the reservoir and convey it to the powerhouse where it is converted into electrical energy. The outlet structure is designed to release the excess water from the reservoir.11. What are the types of dams based on the materials used?
- A. a. Gravity dams, arch dams, and buttress dams
- B. b. Concrete dams, masonry dams, and rockfill dams
- C. c. Embankment dams, concrete dams, and composite dams
- D. d. Concrete dams, earthfill dams, and rockfill dams
Discuss this questionShow answer & explanation
Answer: D. d. Concrete dams, earthfill dams, and rockfill dams
Explanation: Dams can be classified based on various factors such as materials used, design, purpose, and location. Based on the materials used, dams can be classified as concrete dams, earthfill dams, and rockfill dams.12. What are the functions of a dam?
- A. a. To store water, generate electricity, and control floods
- B. b. To provide irrigation, prevent erosion, and store water
- C. c. To provide water for domestic and industrial purposes, control sedimentation, and generate electricity
- D. d. To provide water for drinking, protect wildlife, and provide recreational opportunities
Discuss this questionShow answer & explanation
Answer: A. a. To store water, generate electricity, and control floods
Explanation: The primary functions of a dam are to store water, generate electricity, and control floods. Dams are also used for various other purposes such as irrigation, water supply, recreation, and wildlife conservation.13. What is seepage control in dams?
- A. a. Preventing water from flowing over the top of the dam
- B. b. Preventing water from flowing through the dam
- C. c. Preventing water from eroding the foundation of the dam
- D. d. Preventing water from seeping through the dam and its foundation
Discuss this questionShow answer & explanation
Answer: D. d. Preventing water from seeping through the dam and its foundation
Explanation: Seepage control in dams is the process of preventing water from seeping through the dam and its foundation. Seepage can cause the erosion of the foundation and can also lead to the instability of the dam. Seepage can be controlled by providing an impermeable layer in the foundation, by grouting, and by using drainage systems.14. What are the types of gates used in dams?
- A. a. Sluice gates, radial gates, and vertical lift gates
- B. b. Stop log gates, hoistable crest gates, and roller gates
- C. c. Stop log gates, vertical lift gates, and radial gates
- D. d. Hoistable crest gates, butterfly valves, and slide gates
Discuss this questionShow answer & explanation
Answer: C. c. Stop log gates, vertical lift gates, and radial gates
Explanation: Gates are used in dams to regulate the flow of water through the dam. The common types of gates used in dams are stop log gates, vertical lift gates, and radial gates. Stop log gates are used for low-level flow regulation, vertical lift gates are used for high-level flow regulation, and radial gates are used for intermediate level flow regulation.15. Which of the following is not a component of a typical ROR (Run-of-River) plant?
- A. Intake
- B. Penstock
- C. Turbine
- D. Reservoir
Discuss this questionShow answer & explanation
Answer: D. Reservoir
Explanation: Unlike storage plants, ROR plants do not require a reservoir as they utilize the natural flow of the river for power generation.16. What is the purpose of an intake in a hydropower plant?
- A. a) To regulate the flow of water
- B. b) To prevent sedimentation
- C. c) To direct water into the penstock
- D. d) To store water for later use
Discuss this questionShow answer & explanation
Answer: C. c) To direct water into the penstock
Explanation: The intake is designed to divert water from the river and direct it into the penstock which carries it to the turbine for power generation.17. Which method is used for handling suspended loads in a settling basin?
- A. Flushing
- B. Decanting
- C. Sedimentation
- D. Filtration
Discuss this questionShow answer & explanation
Answer: B. Decanting
Explanation: Suspended loads settle at the bottom of the settling basin while the clear water is decanted at the top and directed towards the turbine for power generation.18. What is the concentration approach used for in the design of a settling basin?
- A. a) To estimate the sediment volume in the basin
- B. b) To estimate the flushing frequency of the basin
- C. c) To determine the dimensions of the basin
- D. d) To determine the type of sediment in the basin
Discuss this questionShow answer & explanation
Answer: A. a) To estimate the sediment volume in the basin
Explanation: The concentration approach is used to estimate the volume of sediment that will accumulate in the settling basin and determine the required capacity of the basin.19. What is the purpose of flushing deposited sediment from a settling basin?
- A. a) To increase the power output of the hydropower plant
- B. b) To prevent erosion of the basin floor
- C. c) To prevent the buildup of excessive sediment
- D. d) To improve water quality downstream
Discuss this questionShow answer & explanation
Answer: C. c) To prevent the buildup of excessive sediment
Explanation: Flushing is required to remove deposited sediment from the basin and prevent it from accumulating to a point where it reduces the effectiveness of the basin or causes damage to the hydropower plant.20. What is the purpose of a surge tank in a hydraulic system?
- A. a) To maintain constant water pressure in the system
- B. b) To reduce pressure fluctuations caused by sudden changes in flow rate
- C. c) To store excess water during peak demand periods
- D. d) To release water during low demand periods
Discuss this questionShow answer & explanation
Answer: B. b) To reduce pressure fluctuations caused by sudden changes in flow rate
Explanation: A surge tank, also known as a surge chamber, is a water storage tank that is used to reduce pressure fluctuations in a hydraulic system caused by sudden changes in flow rate. It is typically placed between the pump and the pipeline to absorb excess pressure when the flow rate suddenly decreases, and to supply additional water when the flow rate suddenly increases. Surge tanks can help to prevent damage to pipelines and other components of the hydraulic system caused by water hammer and other hydraulic transients.