Which statement about hydroelectric power plant is wrong?
27 views
Explanation
Fluctuating load demands can be met just by controlling the flow of water using valves and gates. Due to its robust construction, its efficiency does not fall with time. Statement ‘b’ is correct because construction of dam, installation of alternator and turbines are very costly.