Which one of the following statements is not correct for heading and benching method of tunnelling ?

16 views
  • Drilling and mucking can be done simultaneously (Correct Answer)
  • Benching provides a plateform for working on heading
  • Removal of muck from the heading is very easy
  • None of these.

Explanation

Option A is correct.

Drilling and mucking can be done simultaneously by the heading and benching method.

Removal of muck from the heading is the drawback of this method.