Which of the following project scheduling techniques uses a network diagram to depict project tasks and their dependencies?

19 views
  • CPM (Correct Answer)
  • PERT
  • Gantt chart
  • Monte Carlo simulation

Explanation

Answer: a. CPM

Explanation: The Critical Path Method (CPM) is a project scheduling technique that uses a network diagram to depict project tasks and their dependencies. The network diagram consists of nodes, which represent project tasks, and arrows, which represent task dependencies. The CPM method calculates the critical path, which is the longest path of dependent tasks that determine the project completion date.