Which of the following project scheduling techniques uses a bar chart to depict project tasks and their durations?
17 views
- CPM
- PERT
- Gantt chart (Correct Answer)
- Monte Carlo simulation
Explanation
Answer: c. Gantt chart
Explanation: A Gantt chart is a type of project scheduling technique that uses a bar chart to depict project tasks and their durations. The chart displays project tasks on the horizontal axis and the project timeline on the vertical axis. Each task is represented by a horizontal bar that indicates its duration and start and end dates.