Which of the following project scheduling techniques allows for the estimation of task durations with a range of possible values?

17 views
  • CPM
  • PERT (Correct Answer)
  • Gantt chart
  • Monte Carlo simulation

Explanation

Answer: b. PERT

Explanation: The Program Evaluation and Review Technique (PERT) is a project scheduling technique that allows for the estimation of task durations with a range of possible values. PERT uses three duration estimates for each task: optimistic, most likely, and pessimistic. PERT calculates the expected duration for each task based on these estimates and uses a network diagram to depict task dependencies and the critical path.