Which of the following is not a component of the Work Breakdown Structure (WBS)?
17 views
- Deliverables
- Milestones
- Budget (Correct Answer)
- Activities
Explanation
Correct answer: c) Budget
Explanation: Budget is not a component of the Work Breakdown Structure (WBS). The WBS typically includes deliverables, milestones, and activities that are needed to complete the project. The budget is a separate component of project planning and is typically represented in a cost estimation document.