When tested with the Vicat apparatus, the initial setting time of ordinary Portland cement should be not less than:
7 views
- 30 minutes (Correct Answer)
- 10 minutes
- 60 minutes
- 600 minutes
Explanation
Standard specifications for OPC require an initial setting time of at least 30 minutes, giving time to mix, transport and place concrete. The final setting time should not exceed 600 minutes.