What is the main purpose of a settling basin (desander) in a run-of-river hydropower project?

6 views
  • To remove suspended sediment and reduce abrasion of turbine components (Correct Answer)
  • To store water for daily peaking operation
  • To dissipate energy at the tailrace outlet
  • To regulate river flow downstream of the dam

Explanation

Himalayan rivers carry heavy suspended sediment, much of it hard quartz, which erodes turbine runners, nozzles and guide vanes. The desander lowers the flow velocity so that particles above the design size settle out and are flushed away.