What is the discount rate used for in engineering economics analysis?
18 views
- To determine the cash flow of a project
- To calculate the payback period of a project
- To calculate the present value of a future cash flow (Correct Answer)
- To determine the future value of a present cash flow
Explanation
Answer: c) To calculate the present value of a future cash flow
Explanation: The discount rate is the rate used to calculate the present value of a future cash flow. It is used to take into account the time value of money and the risk associated with the investment.