True about critical path method are all except
24 views
- Network analysis
- Longest path
- Cannot be delayed
- Shortest path (Correct Answer)
Explanation
The correct answer is:
D. Shortest path
The Critical Path Method (CPM) involves identifying the longest path in a project schedule, which dictates the minimum time required to complete the project. Tasks on the critical path cannot be delayed without affecting the overall project timeline. Therefore, "Shortest path" is not true for CPM.