True about critical path method are all except

24 views
  • Network analysis
  • Longest path
  • Cannot be delayed
  • Shortest path (Correct Answer)

Explanation

The correct answer is:

D. Shortest path

The Critical Path Method (CPM) involves identifying the longest path in a project schedule, which dictates the minimum time required to complete the project. Tasks on the critical path cannot be delayed without affecting the overall project timeline. Therefore, "Shortest path" is not true for CPM.