Time taken for any project is estimated by:
- Work sampling
- Input-output analysis
- Network analysis (Correct Answer)
- Systems analysis
Explanation
Correct Answer :- C. Network analysis
[Ref. Park 23/e p872]
• Network Analysis: Is the graphic plan of all events and activities to be completed in order to reach an end objective.
Two common types of network technique are:
– Programme Evaluation and Review Technique (PERT): An arrow diagram representing the logical sequence in which events must take place. It aids in planning, scheduling and monitoring the project; allows better communication between various levels and helps furnish timely, updated progress reports
– Critical Path Method (CPM): The ‘longest path’ of the network is called as critical path. If any activity along the
critical path is delayed, entire project will be delayed