The technique for establishing and maintaining priorities among the various jobs of a project, is known

17 views
  • Event flow scheduling technique
  • Critical ratio scheduling (Correct Answer)
  • Slotting technique for scheduling
  • Short interval scheduling.

Explanation

Critical in the sense that activities under this path are the priorities and cannot be delayed. The delay of any of the activities in this path is directly delay the whole project.