The main outputs of which process include a risk register, risk report, and project documents updates?

13 views
  • identifying risks (Correct Answer)
  • planning risk management
  • planning risk
  • monitoring risk

Explanation

Identifying risks involves determining which risks are likely to affect a project and documenting the characteristics of each. The main outputs of this process are a risk register, risk report, and project documents updates.