The initial setting time of Ordinary Portland Cement (OPC) should not be less than:
14 views
- 30 minutes (Correct Answer)
- 45 minutes
- 60 minutes
- 90 minutes
Explanation
As per standard specifications, initial setting time of OPC must be at least 30 minutes to allow proper mixing, placing, and finishing before hardening begins.