PERT is which type of management technique?
- Based on behavioral science
- Qualitative
- Quantitative (Correct Answer)
- None of the above
Explanation
Correct Answer:
C. Quantitative
Explanation:
PERT (Program Evaluation and Review Technique) is a quantitative management technique used in project management to analyze and represent the tasks involved in completing a project. It is primarily used to estimate the duration of a project by considering the time required to complete different tasks and their dependencies.
A. Based on behavioral science: PERT is not based on behavioral science; it is a tool for time and task management.
B. Qualitative: PERT is not qualitative; it uses numerical data and statistical methods.
D. None of the above: This is incorrect as the correct answer is C. Quantitative.
Thus, C. Quantitative is the correct answer.