PERT is which type of management technique?

26 views
  • Based on behavioral science
  • Qualitative
  • Quantitative (Correct Answer)
  • None of the above

Explanation

Correct Answer:
C. Quantitative

Explanation:
PERT (Program Evaluation and Review Technique) is a quantitative management technique used in project management to analyze and represent the tasks involved in completing a project. It is primarily used to estimate the duration of a project by considering the time required to complete different tasks and their dependencies.

A. Based on behavioral science: PERT is not based on behavioral science; it is a tool for time and task management.

B. Qualitative: PERT is not qualitative; it uses numerical data and statistical methods.

D. None of the above: This is incorrect as the correct answer is C. Quantitative.

Thus, C. Quantitative is the correct answer.