Mixing zinc phosphate cement on a frozen glass slab (-6 to -10 C) is primarily done to:
- Decrease the solubility of the set cement
- Increase working time and allow more powder to be incorporated (Correct Answer)
- Reduce the acidity of the freshly mixed cement
- Increase the setting time in the mouth
Explanation
The reaction between zinc oxide powder and phosphoric acid liquid is strongly exothermic, and heat accelerates the setting. Mixing on a cool or frozen slab dissipates this heat and slows the reaction, greatly increasing working time (by several minutes). Because the matrix forms more slowly, the operator can incorporate about 50-75% more powder for a given consistency, which increases strength and reduces solubility as secondary benefits. Once the cement is placed in the mouth, setting time is actually shorter than with conventional mixing, which is useful clinically, for example when cementing multiple-unit bridges. A recognised disadvantage is moisture condensation on the frozen slab, which can dilute the liquid. Powder is classically added in small increments over a large area of the slab for the same reason - to dissipate heat. The freshly mixed cement remains acidic (pH about 2 at 2 minutes) whichever technique is used.