______is the amount provided in the estimate and bill of quantities for some specialized work to be done by a specialized firm; whose details are not known at the time of preparing estimate.

28 views
  • Provisional sum (Correct Answer)
  • Capital Cost
  • Prime cost
  • Building cost index

Explanation

The work like installation of the refrigerating machine; installation of a lift, air conditioning, etc., for which full information and details may not be known at the time of preparing the estimate and entering into a contract and are required to be installed by a specialized firm, a sum.