In which type of construction contract is payment made on the basis of measured quantities of work multiplied by the rates quoted by the contractor?
18 views
- Item-rate (unit-rate) contract (Correct Answer)
- Lump-sum contract
- Cost-plus-percentage contract
- Turnkey contract
Explanation
In an item-rate contract, the contractor quotes a rate for each item in the bill of quantities, and payment is based on the actual measured quantities executed. In a lump-sum contract, a fixed total price is paid for the defined scope.