In the critical path method of network analysis , the critical path is
32 views
- Shortest
- Longest (Correct Answer)
- Cheapest
- Costliest
Explanation
Correct Answer: B. Longest
The critical path is the longest distance between the start and the finish of your project, including all the tasks and their duration, which gives you a clear picture of the projects actual schedule.