In rate analysis, which of the following is not included in the calculation of item rate?
16 views
- Cost of materials
- Labour cost
- Contractor’s profit
- Site topography (Correct Answer)
Explanation
Rate analysis includes materials, labor, equipment, and contractor’s profit, but site-specific factors like topography are considered separately in overall cost or contingency.