In CPM, the critical path is:
16 views
- Path with minimum cost
- Path with maximum slack
- Longest duration path (Correct Answer)
- Shortest activity path
Explanation
Critical path determines total project duration and has zero slack.
Critical path determines total project duration and has zero slack.