In an activity-on-arrow (AOA) network, a dummy activity is one that:
17 views
- Has the longest duration in the network
- Uses resources but takes no time
- Has zero duration and is used only to show logical dependency (Correct Answer)
- Always lies on the critical path
Explanation
A dummy activity consumes neither time nor resources. It is drawn as a dashed arrow to show correct precedence relationships or to avoid two activities sharing the same start and end events.