In an activity-on-arrow (AOA) network, a dummy activity is one that:

17 views
  • Has the longest duration in the network
  • Uses resources but takes no time
  • Has zero duration and is used only to show logical dependency (Correct Answer)
  • Always lies on the critical path

Explanation

A dummy activity consumes neither time nor resources. It is drawn as a dashed arrow to show correct precedence relationships or to avoid two activities sharing the same start and end events.