In a software project, COCOMO (Constructive Cost Model) is used to estimate

26 views
  • effort and duration based on the size of the software (Correct Answer)
  • size and duration based on the effort of the software
  • effort and cost based on the duration of the software
  • size, effort and duration based on the cost of the software

Explanation

The basic COCOMO equations take the form
Effort Applied (E) = ab(KLOC)bb [ person-months ]
Development Time (D) = cb(Effort Applied)db [months]
People required (P) = Effort Applied / Development Time [count]
//Source:Wikipedia
As it can be observed from above equations,Effort and Duration are on L.H.S whereas KLOC(Line of code) ,used to measure program size is on R.H.S. Hence, Answer is A