In a project planning and design phase, which of the following is NOT typically considered during the project feasibility analysis?

23 views
  • Environmental impact assessment
  • Financial analysis
  • Social impact assessment
  • Project scheduling (Correct Answer)

Explanation

Answer: D. Project scheduling

Explanation:

During the project feasibility analysis phase, various factors are considered to determine whether the project is technically feasible, economically viable, and socially and environmentally sustainable. These factors typically include environmental impact assessment, financial analysis, and social impact assessment. However, project scheduling is typically considered in the project planning and implementation phase, not in the feasibility analysis phase.