If a project is delayed due to unforeseen site conditions, the contractor is entitled to:
15 views
- Termination only
- Extension of time and possibly compensation (Correct Answer)
- No relief
- Penalty
Explanation
Contract conditions generally allow extension of time (EOT) and sometimes compensation for delays beyond contractor’s control.