If a project has 100 KLOC and productivity is 10 KLOC/person-month, estimated effort is:
13 views
- 5 person-month
- 10 person-month
- 100 person-month (Correct Answer)
- 1000 person-month
Explanation
Effort = Size / Productivity = 100 / 10 = 10 person-month? wait correction: 100 KLOC ÷ 10 = 10 person-month → correct answer is B.