f the peak load on a power plant having a capacity of 100 MW is 70 MW during a given week and the energy produced is 58, 80,000 kWh, the capacity factor for the plant for the week will be ___?
13 views
- 50%
- 35% (Correct Answer)
- 65%
- 60%
Explanation
Capacity factor = Average load/ Plant capacity
Average load = Energy produced / Time (in hours) = 58,80,000 / 7 x 24 = 35000 kW
C.F = 35 MW / 100 MW = 0.35 (or 35%).