All are true regarding Critical Path Method (CPM) except
17 views
- Is a part of Input-Output analysis (Correct Answer)
- Visualised in graphical representation of all events/activities carried out
- Is the longest part of the network
- Any delay in CP delays whole project
Explanation
Correct Answer :- A. Is a part of Input-Output analysis
[Ref. Park 23/e p871-872]