A software development project has a total of 10 milestones. The project manager wants to use the critical path method to determine the earliest possible completion time for the project. The following table shows the duration of each task and its predecessors:<br>What is the earliest possible completion time for the project?
24 views
- 16
- 17
- 18
- 19 (Correct Answer)
Explanation
Answer: d) 19
Explanation: The critical path method involves finding the longest path through the network of tasks. We can start by calculating the earliest start and finish times for each task:
The earliest possible completion time for the project is the earliest finish time of the last task, which is 18+1 = 19. Therefore, the correct answer is option d) 19.