A road project has a present value of benefits of Rs. 15 crore and a present value of costs of Rs. 12 crore. What is its benefit-cost ratio, and what does it indicate?

6 views
  • 0.80; the project is not economically viable
  • 0.30; the project is not economically viable
  • 2.70; the project is highly viable
  • 1.25; the project is economically viable (Correct Answer)

Explanation

B/C ratio = PV of benefits/PV of costs = 15/12 = 1.25. A B/C ratio greater than 1 means benefits exceed costs, so the project is economically justified.